New B & M Store at Mablethorpe

HWA have completed structural & civil design for a new B & M store in Mablethorpe.

The building is undergoing a 10-week internal retail fitout ready for the opening date, which is expected to be around the end of July 2023.

Built on a vacant site next to a substantial new housing development, the single storey steel framed retail unit has elevations clad in masonry and micro rib composite.

As part of our appointment, we undertook a Flood Risk Assessment and Drainage (SuDs)  strategy for planning submission purposes. As the site is by the sea, the ground is extremely soft, so we implemented ground improvement techniques for foundations and floor slab. The site was also found to be at risk of flooding.

Our image show the site under construction in January 2023.